900m of trenching!

We have been asked to quote to dig a trench 1m deep by 300mm by 900 meters long for a ground source heat pipe. The trench will be in an open field and will be using a 3 tonne digger although have access to larger equipment if needed. The question is how much do you think it will take to dig this trench?  We will anticipate that the ground is not on bedrock!

Thanks 

Andrew

You need to be a member of Landscape Juice Network to add comments!

Join Landscape Juice Network

Votes: 0
Email me when people reply –

Replies

  • PRO

    Can you hire in a trenching machine? Be far faster than the digger and easier to reinstate after?

  • Hi adam. I dont know of any i could hire localy. The job is located by Shrewsbury. How much quicker would a trencher be?

    • PRO

      A hell of a lot quicker there's plenty of videos on youtube of trenchers of various sizes. A skid steer with a trencher will be a bit more common than a dedicated trencher for hire though.

  • Kanga loader with trencher?? Lots of hire shops have these! Otherwise surely a bigger digger would be quicker and more economical??
  • With a 3 tonner I reckon id get that done in 2 days, then reinstated in a further day I reckon. But to price id put the dig out at 3 just incase.  

  • Try your local golf clubs, they regularly use trenchers for irrigation or drainage and may be able to point you in the right direction.  This sounds a good way to lose a lot of money if you are not careful, personally I would get a specialist company in to quote and maybe manage the works.

  • ground source is not done usually  using a trencher, as 2 pipes are usually in the trench with a gap between , 300mm is a unusual  trench as  as pipes are normally min800mm apart to stop frezing , 800 bucket pipe on each side of trench

    i would say 3 days poss 4 for a good man

    • Well done Mark, always someone who knows what they are talking about! ;-)

      • its a simple job for a compitent digger operator, i would not price it on a day rate, no money to make, it would be a price job per linear metre,hit it hard and draw the bucks  myself 3 days done and finished